Distributed wind power development: how to break the shackles to realize the potential?

  • Category:
    Industry News
  • Browse number: ...
  • Release time: 2025-10-16
China's decentralized wind power has been slow to develop since its start in 2012, but the wind industry is eager to replicate the successful experience of distributed photovoltaics due to the severe impact of large-scale projects. Distributed wind power, although the total capacity is small, can take advantage of the existing power grid in transmission have been completed, more flexibility, achieving the effective utilization of wind energy resources scattered and given on the spot. Because of this, China's distributed wind power has great potential for development.
 
Distributed wind power development: how to break the shackles to realize the potential?
 
Decentralized wind power projects are a unique type of onshore wind power projects in China. According to the definition of the national energy administration at the end of 2017, the distributed wind power refers to the wind power project with an access voltage level of 35kV and below, which is completely consumed in the local area and does not send electricity to the high voltage level.
 
, distributed wind power currently in China's wind power capacity of less than 1%, but for the need to improve the development quality and optimize the layout of the Chinese wind power industry, development of distributed wind power is to improve the utilization rate of wind power, the inevitable need to promote industry development. The relative lag of its development level indicates the great potential of development.
 
The has obvious advantages, but distributed wind power has been slow to develop in China, the projects have been put into operation in the capacity of less than 1% of the total capacity of wind power grid, is far less than the construction scale of Europe. According to qin haiyan, secretary-general of the China renewable energy association's wind energy committee, there are two main reasons for this:
 
One is wind power development in China started in the west, large wind power development companies used to through massive investment in terms of centralized development, individual distributed wind power projects of small, relatively low investment success, enterprise's enthusiasm is not high.
 
Distributed wind power development: how to break the shackles to realize the potential?
 
The second is that the decentralized wind power project still adopts the approval requirement and process of centralized development, which leads to low efficiency and increased up-front cost.
 
In addition, China has not formed a relatively perfect standard system and management standard of distributed wind power technology to guide the overall development of distributed wind power. This includes unclear definitions of wind power, and the current definition is too broad to lead to differences in understanding. The development of decentralized wind power planning and power consumption in provinces and regions is lagging behind, and government guidance is not enough. The promotion of distributed wind power does not combine with the development of county economy, especially the interests of rural and peasant households, etc.
 
In order to solve the above problems, qin hailu believes that the development of decentralized wind power must adhere to the ideas and principles of "centralized planning, batch approval and integration with local economic development".
 
First, decentralized wind power projects are decentralized and small, and must be centrally planned so as to achieve economic and efficient management and ensure the orderly development of projects.
 
Distributed wind power development: how to break the shackles to realize the potential?
 
Second, the project should be packaged and approved in a county area to simplify the early procedures and avoid unnecessary costs.
 
Finally, can be based on the experience of the foreign community wind power development, through the land, the PPP mode, and so on ways to increase local participation, and will be distributed around the wind power development and tourism development, the characteristics of small town construction, the people's livelihood improvement works, such as, the combination of the local community and residents benefit, promote local economic and social development.
 
According to the 13th five-year plan for wind power development, by the end of 2020, wind power generation will be guaranteed to reach 420 billion kilowatt-hours, or about 6% of the country's total electricity generation. Immediately, the national energy administration issued by the middle of 2017's "about accelerating distributed access to wind power project construction related requirements" puts forward, distributed access wind projects to meet the requirements, without being limited by the scale of annual guidance, were seen as key symbol of distributed wind power into the fast lane.
 
And published in the march of the 2018 energy work guidance on notice for further pointed out the direction of the wind power development: focus on solving the problem of clean energy given to priority to the development of distributed wind power. From the demand side, the development of wind power in China has gradually shifted to the central and eastern regions, and distributed wind power is the new main force. With the characteristics of close to load and short construction period, the dispersive type will continue to spread in central China as the core increment of wind power. The detailed rules for future development of distributed wind power are expected to be issued as soon as possible.
 
Obviously, although the development of decentralized wind power in China has been slow in recent years, the development of decentralized wind power is the general trend. Today's distributed wind power, with policy support and market demand, is likely to become the next industry outlet.
url: http://www.baihongdq.com/en/news/32.html

Related News

Address: In the Jinyi New Energy Industrial Park on the east side of Huanzhen Road, Jiaze Town, Wujin District, Changzhou City 

Copyright:Jiangsu Baihong Intelligent Electrical Co., Ltd     苏ICP备18016683号-1    Powered by zzw

在线客服

online service

Hello, I am the online customer service

X